The Renews Podcast features Stephen Dunn speaking with Matt Hagg, the project director of the Narnaguiha offshore wind farm. The project encountered significant challenges, such as unexpected soil conditions, drilling problems, and delays in turbine installation due to electrical system issues. Various setbacks, including losing a drill and the need for a new vessel, prolonged the construction timeline, leading to completion in 2025 instead of the initially planned three years. Despite doubts about project completion, the team's perseverance and collaboration with shareholders, lenders, and advisors played a crucial role in overcoming obstacles and successfully finishing the project. Matt Hagg emphasizes the importance of working with the right people and advises perseverance in the face of challenges, highlighting the ultimate success of the project despite the adversities faced during construction.
Transcription
3939 Words, 21647 Characters
Welcome to the Renews Podcast, with me, Stephen Dunn. There were times when we felt this project must be cursed. There were people talking about, there must be a suboter in the lines. Whatever you can come up with, you know, to think of, what is the explanation of so many things going wrong on that one project? I'm here with Matt Hagg, the project director of Narnaguiha, or NNG, as it's home to being on. Matt, you're very welcome to the Renews Podcast. Thanks very much, Stephen. I want to start by saying congratulations on winning a prestigious project of the year award at the Scottish Green Energy Awards. What do you think it is about the project that the judges liked? And why do you think the project deserves that title? I think outstanding project, well, there are various reasons why the project is outstanding. It's one of the very early projects. But I think the main feature is how many difficulties we have overcome over the years to get the project from where it was to being an operational project and having 450 megawatt operating there, producing power for almost 400,000 people, you know. So there were a lot of things that went wrong. And I think I'm really proud of the team to stick with all of that, with all of that tenacity and get the project finished. Because there were a lot of adversaries, I'm sure we're talking about some of them today. And we had very little turnover in the team. And I'm really proud of them to have finished it. And I think that sense of pride is also with the team. And so we're very thankful for getting this award. Well, let's go back and maybe talk about some of the challenges. So you obviously come into the project and you and the team deliver financial flows in November 2019, which is a big milestone in and of itself. But going forward from 2019, you run straight into the pandemic in 2020. Can you tell us about the impact that that had at that initial stage when you were very early in construction? I think it was quite shocking at the beginning, to be honest, because as you said, we had, or I had at least about a year of building the team, getting to financial close, getting all these major contract signed, a lot of negotiations, and also bringing the lenders on board. And at the same time, actually a new shareholder was coming on board, ESB joined EDF in a 50/50 deal to build this project. So I would say it went quite smoothly until November 19, when financial close took place, and everybody was looking forward to build this project as planned in about three years. But then, as you said, early 2020, Covid hit, it became clearer that soil conditions were maybe different than what we had expected. And I think it was a big shock to the system, to shareholders, to the team, probably to lenders, when they heard about the scale of things that were happening. And it took a bit longer, obviously, to really sink in what do these different soil conditions mean? And after a lot of long discussions with SyPAM, we came to an understanding, but it took a long time to get there. So you started offshore drilling in August 2020. I think, and SyPAM was your lead foundations contractor on the project responsible for installation. How quickly, after you began drilling, did it first emerge as a problem? And why did you take that decision to pre-drill for pinpoils for your jackets? I think it took a few drilling holes, I would say, to come to that realization. But overall, in the scale of things, it became clear relatively quickly. After you drill a few holes, you expect some initial things that go wrong, but fairly quickly, after a few holes, it became clear that the drilling speed was not quite what we expected, that the hole set up probably was a little bit more complex and need more adjustments than we originally thought. And therefore, the whole drilling campaign would take longer than we had expected. I think the decision to drill these pinpiles and then come with the jackets and lift them on top of the pinpiles was the correct one. But we're still talking, you know, when people talk pinpiles, I don't know what image they have in their mind, just to be clear, this is a three meter pile, you know. So it's a big hole. You drill in 55 meter depth underwater, remote controlled with a lot of large equipment weighing actually thousands of tons to drill these holes. I think the principal decision was right for the site and for the complexity of the ground. But there was probably an underestimation how many challenges you could find in the ground because we did a lot of soil campaigns. We did have a lot of information about the soil. We knew that the soil was complex, but we didn't know how different it would be even within a very small radius. So our jackets have about 30 meter distance between the pinpiles or between the legs of the jacket. And we found that within these 30 meters, the rock may be at very different levels. And that made it quite complex because the design did assume, of course, certain margins, but it fell outside these margins of what was calculated. And that meant not only did we have to adjust the calculations and the design, but we also had to physically change things how we did them offshore. And that had quite an impact on the project. It wasn't only the challenge with the seabed that you had, of course. I think you lost the drill at some point as well, which also had an impact. Can you talk us through how that happened and what impact it had on the campaign? Well, I remember very well the call I had from the construction manager saying, we think we may have lost the drill. And I thought, that's impossible. We're talking about a 17 meter equipment weighing hundreds of tons. And we had one of the largest construction vessels in the world out there, the S7000, which has two cranes being able to pull 7000 tons each, basically. So you can basically lift the Eiffel Tower, is that thing? And yet we couldn't pull out that drill anymore. And we tried for a number of days, maybe in a couple of weeks, different ways of pulling in different directions and wiggling it a bit around. And it just wouldn't move. For me, that was really a freak event, I have to say. Because we will never find out what exactly stopped it. We can only think that it's probably some kind of rock jamming into the machine and thereby stopping it from moving. But we drilled over all, I think, more than five kilometers of these, these holds. And we never had any issue like that anymore. So I think my observation that it's a freak event is probably correct. At the same time, this set the project back immediately by about a year because you need to build this new drilling machine. And yeah, just to be clear, when we talk about the drill, people think probably of a household drill. This is, of course, something very different. It's a huge machine that has hydraulic engines, electric engines. It has pumping tubes and all these things in it. So as I said, it's very complex and it takes a lot of time to rebuild it. When you look back on the decision to take this strategy of drilling, which at the time was probably not unique, but perhaps novel in offshore wind to drill so many locations in such a campaign. What's your view on that decision given the campaign was so challenging and ran so over-programmed? Well, you have to look at the alternatives as well, I guess. What would be the alternatives? You could do a gravity base. We couldn't really do monopiles because of the tankal surroundings. We did think about suction piles or suction buckets. And I know a neighbouring wind park has done that successfully, actually. But I think our soil conditions would have not been. We wouldn't have been able to use them in the soils that we had. So even in hindsight, I think the principle design decision to go with drilling and the jacket was probably the correct one. But maybe we underestimated, of course, the technical novelty, as you said, at this scale, at the size of piles and in the soils that we actually had, of what we would encounter. Just to close out on the drilling in overall sense. When you first started, how long did you expect it to last from August 2020 and how long did it end up running for? Oh, no, you're challenging me. My memory, I think. Ballpark. Originally, we planned like a season to a year, I think, for the drilling. You know, that was when it's supposed to be finished. And there were times to be clear where we drilled a hole, probably in a day or something, you know, so more or less in the times that we expected. But there were other times where we spent like weeks on a hole, because of various issues that happened that were unforeseen. And we ended up, if I'm not mistaken, having the last jacket installed, maybe in 23. So I think October 23 probably was the last jacket installed, yes. So it took a lot longer. But your jacket installation effort goes well, relatively speaking to the actual drilling for the pin coils, right? Yes, it did. It was fairly straightforward. I mean, there were issues as well, but in comparison, it went very well. I would agree. So you get over the drilling campaign, your jackets go well, you start putting up turbines, your offshore topsoids and jackets go out. You turn on the electrical system on what happens next? Well, unfortunately, we had a few electrical issues, as you know, we weren't able to provide the grit as quickly as we thought we would be able to do. That wasn't for the cables. The cables actually went in fine, but some of the electrical equipment and the electrical system had issues that needed to be resolved, which meant that we had to reinstall some items and we had to remanufacture actually some items, which of course takes time, which also means you need to bring in generators offshore. These generators then have to be fueled on a regular basis. And all of this, of course, adds complications. It adds cost and it adds time. So unfortunately, when we were finally starting to install the turbines, we didn't have the ability to provide them with grit. So they stood there for quite an extended time on generators, because they need some power to be maintained basically. And we couldn't produce a power that we wanted to produce. And that was certainly one of the low points of the project. Now, back to the show. The weather starts to turn against you in late 2023 as you're pulling turbines out. You have obviously vessel windows for contracted vessels and it becomes clear heading into late 23 and into 24 that you won't finish installation of the turbines. Can you take us back to that period and the realization, landing on what you faced in the market, then to try and bring in a new vessel to finish the project? Maybe I have to take one step back there because the whole vessel program, of course, was upset by the foundations again. So what we did is we repurposed the vessel blue turn, which we used for the installation or had planned for the installation of the turbines. We repurposed it to help with the drilling campaign. So that took place over a whole year where SIPAM used a different vessel than was planned for installing jackets still. But then as you say, you also have to find different slots now for actually not only installing turbines but also laying into array cables and all these things. So the whole vessel campaigns become quite complex because they go differently than planned. We had originally allowed for contingency. We had allowed times where we wouldn't have used a vessel, but unfortunately that contingency was used up with the issues we encountered in drilling. So finally, I don't think that was like the step change thing in one day. Like we had on the drill, you know, you get this call and something dramatic happens. Here it was more a realization, as you said, with the weather progressing, with the installation progressing slower than what we had expected. I think by that time we were already quite conservative in our planning because of all the issues we had encountered. So we started looking fairly early, okay, what other vessels would there be maybe available if we were not able to finish that campaign? And well, we found vessels unfortunately not as quickly as we were hoping for, but of course it was very disappointing to shareholders, to the team, to the lenders, that we weren't able to finish that campaign off turbine installation in the time we had planned. So you move in into 2024, you find a new vessel eventually in late 24 and you're able to get back out on the water and finish the project in 2025. Although you say, I remember talking to you in 2019 and saying to you, why is it going to take you three years to build a 450 megawatt offshore wind farm? It's very conservative, like you just said. I mean, reflecting on the fact it took you five years now. You know, what are the lessons that you're taking from the project and that you've learned along the way in terms of executing an offshore wind farm with this scale? Yeah, there are probably a few, I mean, nothing will sound like completely new, but if you experience it, you see the value of these lessons to plan for the unexpected. You know, always in everything you do, something can happen that is completely unexpected. And I think I said it to you earlier, I compare it to other projects I've been involved with and some of them, to a large degree, the same management team. So experience people, some of them have been involved in ten offshore wind parks and more. And yet, something unexpected happens and you have to deal with it. Now, it's a benefit if you have the right experience people on board to be able to deal with the unexpected. But in the end, you need more time and you need more money. There's no way around that if these issues happen. And unfortunately, that can happen in offshore wind parks. You enter COVID, you enter jacket drilling issues, you enter electrical issues, fabrication issues, installation issues offshore. I mean, this is not normal for in the recent history of UK offshore wind, perhaps European offshore wind. How did you deliver the project with all of these things going on? Well, we try to stay calm and deal with one issue after the other, you know. It was quite challenging at times, I would say, and people face these issues. And you talk about it together, of course. You try to find solutions. Contractors can get very frustrated because they had their own plans. They have to re-plan, as you said, vessel become unavailable. You have even more issues than you mentioned there, you know, like little accidents and yards which delay the vessel being delivered again and all that. You said earlier, yeah, the vessel was supposed to come at the end of 24. It actually arrived early 25. There were various reasons for that again. But I think the only way to deal with it is, is look at each issue, try and resolve it calmly, try and keep everybody informed in a transparent way. Certainly towards the board and the lenders. And I think in the end, everybody then realizes, yes, this is a reality we're facing here, even though we don't want to face it. But the team is doing the right things to solve the solution, to solve the problem and find a solution to it. As a journalist, following the project, going back far too many years, perhaps back to the early days of the project under the mainstream ownership. There was a sense during construction, certainly picking up conversations in the market. People were skeptical as to whether the project would ever get finished or ever be delivered. And whether it could be the first failure, let's say, in construction of an offshore infirm, was there ever a time where you felt we're in a sticky situation here and we may not get to the end? For sure, there were times. There were times when we felt this project must be cursed, you know, and there were people talking about there must be a suboter in the lines. Whatever you can come up with, you know, to think of what is the explanation of so many things going wrong on that one project. And as you said, there's even a history with mainstream and challenges at that time and so on. Did I ever think it wasn't going to be built? I think when we had the issue with the soils in the beginning, and we weren't sure that we would find a good technical solution to it, there was a chance probably looking at that. At the same time, I always felt we were lucky to have these two strong shareholders who clearly want to build offshore windparks, who stood and stand behind the project and wanted to make it a success. So I think there were small doubts at times, but they were very brief and in the end we managed to do the refinancing. We managed to find a technical solution and we managed to do it actually with the contractors we started with, which I think ultimately was the right thing to do and a good decision. When you are after coasts now, of these coasts of Scotland, and you've been out there and you see the project, now it's completed instruction, what are the things you'll personally take from this project into future projects? Well, as I said, I can't help a sense of pride when I look at it and thinking, well, that took in my case actually seven and a half years on the project to get as there. What would I take forward? I think see that you work with the right people, that you have the right people in the team, and that you also have the right people to work with, be it on the shareholder, on the lender, on the advisor's side, in the end, it's about people. And if you got the right ones on board, I think you will solve the problems and you will bring a project to success. The sector is going through a difficult moment where developers are walking away from projects. You've gone through a project where you've really dealt with endless stream of challenges in the actual construction of a project and got there. You've persevered. Is there anything that you can take from the project or that you can say to the rest of the sector? That is a message from such a difficult campaign and know that you've got there. Well, as you said, perseverance is important. I'm old enough to say I've seen a few cycles. I know right now we're probably in a bit of a valley, but I'm absolutely convinced we'll see the industry's thrive and go forward again. And in a few years' time, the world will look very different out there. So if people find themselves in this situation, I would say, hang in there, persevere and you will be successful. In terms of like to dust a settle now on all the decisions that you and the team made during the last seven or eight years, is there anything that you would look back on? We talked about drilling and that being the right decision, ultimately, but is there anything else around the projects that you would say? I would have done that a bit different. You know, at the time when you're trying to get contracts closed, you come to financial close and so on, there's always a big rush. You know, everybody has very tight timelines, everything should happen as quickly as possible because it's very important to get to financial close. Maybe if you take a little bit more time in the beginning, you could think a few things through, you could maybe spend a bit more time in planning ahead, but I also know the reality is when you're in that situation, and people want to get to financial closer, want to close these contracts. And is it realistic that you sit back and say, actually, it's better now to take another half a year to investigate these soils more or to look at more details in the design? It probably isn't, you know, so it's a nice thing to say, yes, it would be nice to have more time, but the realities of project finance and of project development are probably not allowing it even in the future. So you're in commercial operations now. Can you tell us about how that's going? And if the project is matching the expectation in terms of power and performance? Yeah, let's talk about some positives. We didn't mention the safety performance of the project, which was actually excellent. We have an LTRF of less than one, which is good in any comparison of offshore construction, I think so that went very well throughout the years. And I think everybody and the team worked hard on that. Coming to the operation, again, a very positive story. The Siemens was quite successful in commissioning these turbines relatively quickly. The second campaign of installation vent fairly quickly. And since I think May this year, all turbines are commissioned, are operating and working well. So we now see a fully operational wind park that produces in line with expectations. It has the availability of what it's planned for. And we're basically seeing the money coming in to hopefully pay back all that debt that has been accumulated. But overall, a very positive outcome of all for the operational side of the project. We started by mentioning the awards that's sitting on your desk behind you. Is that the cherry on the cake as it were after a really tough slug? I would say it is, yes. It felt really good to receive that award that people outside the project, let's say, recognised the challenges we went through as a team. And yeah, it was fantastic to see it recognised, especially for the team as well. I think it was a great feeling and it's really, really well-accombed. And I appreciate it. Well, Matt, I'm sure you'll put your feet up over Christmas and it's a well-deserved. Thanks very much for being on the podcast. Thanks very much, Steven, for the pleasure. stop is.
Podcast Summary
Key Points:
The Narnaguiha project faced numerous challenges during construction, including soil conditions, drilling issues, and electrical system problems.
The project experienced setbacks like losing a drill, delays in turbine installation, and the need for a new vessel.
Despite the challenges, the project was eventually completed in 2025 after encountering various obstacles over the five-year construction period.
Summary:
The Renews Podcast features Stephen Dunn speaking with Matt Hagg, the project director of the Narnaguiha offshore wind farm. The project encountered significant challenges, such as unexpected soil conditions, drilling problems, and delays in turbine installation due to electrical system issues. Various setbacks, including losing a drill and the need for a new vessel, prolonged the construction timeline, leading to completion in 2025 instead of the initially planned three years.
Despite doubts about project completion, the team's perseverance and collaboration with shareholders, lenders, and advisors played a crucial role in overcoming obstacles and successfully finishing the project. Matt Hagg emphasizes the importance of working with the right people and advises perseverance in the face of challenges, highlighting the ultimate success of the project despite the adversities faced during construction.
FAQs
The project faced various challenges, including soil conditions, drilling issues, electrical system problems, and vessel availability.
The team tried to stay calm, dealt with each issue one by one, found solutions together, and kept stakeholders informed.
The pandemic caused shock and delays as soil conditions differed from expectations, leading to longer drilling campaigns.
Pre-drilling for pinpiles was necessary due to complex soil conditions and unexpected drilling challenges encountered during the campaign.
Despite losing the drill, the team tried various methods to retrieve it, but the incident set the project back by about a year, requiring the construction of a new drilling machine.
Lessons included planning for the unexpected, the value of experience in handling challenges, the need for more time and money when issues arise, and the importance of having the right team.