Budgeting and Cost Control

from APM Project Management Qualification

6m 39s

Budgeting and Cost Control

Budgeting and cost control are essential for project success, requiring the project manager to establish a detailed financial plan that includes base costs, a contingency fund for known risks, and a management reserve for unforeseen events. Effective cost control goes beyond simple spending tracking by monitoring committed, accrued, and actual expenditures to provide a full picture of financial health. This holistic view helps prevent supplier insolvency due to cash flow issues, which can derail project timelines and increase costs. Milestone payments support supplier stability by ensuring regular funding. Continuous performance evaluation through value assessments enables timely decisions on project continuation, replanning, or termination. Project sponsors play a critical role by reviewing cost data at key decision points to ensure financial viability and alignment with project objectives. Without rigorous cost monitoring, projects risk financial instability, poor supplier relationships, and ultimately, failure. These practices ensure sustainable project delivery and long-term value creation.

Transcription

1213 Words, 6414 Characters

English
Hello and welcome to quantitrainings APMP podcast series podcast 21 possibly budgeting and cost control My name is Adam Montgomery. I'm here my colleague Tim O'Connor. I don't know if he's Gonna say hello. No, he's not okay. So he'll speak to me at the moment about budgeting and cost control and the the assessment criterion Here is to explain what's meant by budgeting cost control So we'll talk a little bit around this subject and why it's important. Go for it then Tim Yeah, so With budgeting you just usual center of the term really you need to plan for how much money you require Throughout the project as a whole and at various intervals in the project And so it's the project manages responsibility to manage the budget and this is part of it And then when the project starts and money is being spent and reports have been generated That will be your cost management and preferably Your costs should be within the plan for budget But because things are estimated And there ought to be a tolerance line really And should the tolerance be exceeded? It's then that you ought to escalate up to the next level of management and the project sponsor Good and how do we come up with this budget? What do we have to take into account when we come out with the initial budgets? APM Recommend three major areas. So the base cost estimate that would be the total of your outputs and all the activities the cost of paying for your resources A contingency and that is a pot to pay for Risks that have been identified. So if those risks were to occur Then the cost is even with those can come from the contingency fund makes sense to have that money set aside because you don't have to go begging if a risk And in addition to that, a management reserve which seems to be hard Initially, but it's there to pay for things that you don't know you don't know and so risks that could not all rums felt Risk that couldn't be identified at the start of the project but again If if you have got some money set aside, you're not going to be caught out in the event that something onto what happens Okay, good so we set a budget and then we shall spend the rest of our Project trying to ensure that we remain within that budget or somewhere except to be close to it It may sound obvious, but why is it that we actually why why is keeping on the budget so important? Because there are questions you know in the examiner around this and then it's tempting to just say Well clearly you need to keep checking your budget How would you how would we say what the shall stop talking Yes, so you need to have an awareness of the cash flow of the customer, but also the cash flow of suppliers And so typically suppliers have to borrow money in order And to pay for their element of serves in your project so to pay the wages and materials And if it's too long a period before you and other companies recompense them It may well be that they don't have the money to pay for their day-to-day cast and they go out of business and Since the economic downturn started a lot of good companies have gone out of business because of poor cash flow And that's just not in the interest of anybody really, you know Certainly not to the supply they go that business, but also the customer because if you need to replace a supplier halfway through That's bound to have an adverse effect on the project So there are things such as milestone payments that can address that risk in that you Recompense the supplier at certain intervals in the project for delivered work So we get some sense of of the funding requirements for a project by by people to a budget and so on Obviously it can prevent They're just going bust. I think one of the big things is that if we have a budget and then monitor costs as they come in again So we can actually prefer perform A calculation such a value. I mean if we're not doing this we can't We don't really get a sense of how we're performing and of course key to all this is that we make sure we are always proceeding with a project's level again if we don't know how much money was spending Constantly keeping an eye on these costs. We may be proceeding with them and in viable or in viable So it's one of the things that the sponsor certainly should be looking at at a gate review So the go-on no-go decision Because if the cost seems to be sparring out of control Then that could be an argument either to replan but or even to curtail the project So when we gather information about what we're spending that there's kind of three Three types if you like or expenditure or potential expenditure three types cost we might need to Take into account the first one is a commitment So this is when we've we've ordered something. So we haven't actually paid for the Goods yet or services. We haven't received them But we have ordered it so obviously maybe subject's contract So maybe if there's anyone out there who's ordered a training course and content But you haven't yet attended yet. You haven't yet paid for it yet We would talk about Um at the same time there'll be money that we debts that you've accrued So work or goods Services have been received, but you still haven't yet paid for it um And the other type is actual expenditure where you pay money out for goods and services you've received so at any one point if you like there are Orders and goods that you've paid for and so on in different stages of this really Um, and you need to be very aware that all of these are going to Become payable at some point Um, so you need to take account of all of them not just when the money Is actually going out of your account something since if you if you add those up Uh, along with nestimate for the remainder of the project at any one point you can reach your Your forecast your latest forecast outturn cost for the project Yeah, so I'm there but certainly used to be uh questions around now I think in in the exam but um Yeah, commitment accrual an actual expenditure or what you need to keep in mind. Yeah, because if you just Focus on actual expenditure that gives you a false picture Um, because there may be money that currently is within the account Of the projects that you know he's ring fenced to be used elsewhere Um, so including all of those costs Good Okay, um all right and symbol that I i'm happy that that's purchasing cost management done and happy if you're happy I'm happy. Let's move on Bye-bye

Podcast Summary

Key Points:

  1. Budgeting involves planning the financial requirements of a project over time, with the project manager responsible for managing the budget throughout its lifecycle.
  2. A comprehensive budget includes the base cost estimate, a contingency fund for known risks, and a management reserve for unforeseen risks not identified at the outset.
  3. Effective cost control requires continuous monitoring of actual, committed, and accrued expenditures to avoid financial mismanagement and project failure.
  4. Poor cash flow management can lead to supplier insolvency, disrupting project delivery and causing significant delays or cost overruns.
  5. Milestone-based payments help maintain supplier liquidity and reduce financial risk during project execution.
  6. Cost performance is assessed through value calculations, enabling informed decisions about project continuation, replanning, or termination.
  7. Project sponsors must review cost data at key gate points to evaluate viability and make go/no-go decisions based on financial health.
  8. Focusing solely on actual expenditures provides a misleading picture; all three types of expenditure—committed, accrued, and actual—must be considered for accurate forecasting.

Summary:

Budgeting and cost control are essential for project success, requiring the project manager to establish a detailed financial plan that includes base costs, a contingency fund for known risks, and a management reserve for unforeseen events. Effective cost control goes beyond simple spending tracking by monitoring committed, accrued, and actual expenditures to provide a full picture of financial health. This holistic view helps prevent supplier insolvency due to cash flow issues, which can derail project timelines and increase costs.

Milestone payments support supplier stability by ensuring regular funding. Continuous performance evaluation through value assessments enables timely decisions on project continuation, replanning, or termination. Project sponsors play a critical role by reviewing cost data at key decision points to ensure financial viability and alignment with project objectives.

Without rigorous cost monitoring, projects risk financial instability, poor supplier relationships, and ultimately, failure. These practices ensure sustainable project delivery and long-term value creation.

FAQs

Budgeting involves planning the total amount of money required for a project over time, including at various stages. It is the project manager's responsibility to establish and manage the budget effectively.

The three key components are the base cost estimate, which covers planned resources and activities; a contingency fund for identified risks; and a management reserve for unforeseen risks not identified at the start.

Cost control ensures that expenses stay within planned limits, helps prevent financial overruns, and maintains project viability. It also supports informed decisions at project review gates.

If costs exceed the tolerance line, the situation should be escalated to higher management or the project sponsor for review and possible action, such as re-planning or project curtailment.

Poor cash flow can cause suppliers to go out of business, disrupting the project. It also affects customer relationships and may require replacing suppliers, which can impact project progress.

The three types are commitment (ordered but not paid), accrual (received but not yet paid), and actual expenditure (money already paid). All must be considered for accurate cost forecasting.